An over-target baseline (OTB) is a comprehensive rebaselining effort that is best categorized as an internal replanning effort.

A. True
B. False

Respuesta :

codiepienagoya codiepienagoya
  • 06-01-2020

Answer:

The answer is "option B".

Explanation:

An OTB stands for an over-target baseline, it is a new management benchmark when an original target can't have coincided and new goals for management purposes are required.

  • It is also known as a reference to the foundation for calculating or constructing.
  • It is an understanding between the client and the contractor that the cost base, which is not part of the original contract budget, should include an extra budget

Answer Link

Otras preguntas

The frequency of data is the higest at
What is the volume? 9 m 19 m 7 m
Clarisa's annual gross pay as an account manager is $54,000. If the graduated state tax rate is 1% for the first $5,000 and 3% for amounts over $5,000, what is
Why do you believe many cancers go unrecognized until after the formation of tumors and/or the person becomes
Funtimes Amusement Park has 750 employees and must hire an additional 28% for the vacation season.what is the total number of employees needed for the vacation
Please help!!!!!!!!!!!!!
Explain any four forms of power sharing
The representative of the reigning monarch of the United Kingdom in both Australia and New Zealand is called the __________. A. prime minister B. governor gener
Taylin buys 5 ounces of tea leaves for 10. At this rate, how much money does she need to buy 12 ounces of tea
what is the prove that 4+3=5​