A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

The novel Uncle Tom’s Cabin, which effectively the unfairness toward black people, was a major influence in the antislavery movement. (A) portrayed…strengthenin
What's the answer to this problem?
The novel Uncle Tom’s Cabin, which effectively the unfairness toward black people, was a major influence in the antislavery movement. (A) portrayed…strengthenin
Ratio equal to the ratio given 12:7
A hiking club has 9 members. How many ways can they choose a president, vice president, secretary, and treasurer from among the members?
The novel Uncle Tom’s Cabin, which effectively the unfairness toward black people, was a major influence in the antislavery movement. (A) portrayed…strengthenin
An astronaut who weighs 126lb on Earth weighs only21lb on the moon. How much would a person who weights 31lb on the moon weigh on Earth?
Examples of cultural diffusion in ancient Rome pertaining to government
How did allies hide from Germans D-day invasion plan?
Which type of twins are likely to interact with each other in the womb a. Non-identical b. Identical c. neither