Jin schedules 496 hours for a project. He plans to work 8 hours each day. How many days will it take to complete the project?​

Respuesta :

penguinlife90 penguinlife90
  • 01-12-2021

Answer:

62 days

Step-by-step explanation:

496/8 = 62

Answer Link
clickykeyboardasmr
clickykeyboardasmr clickykeyboardasmr
  • 01-12-2021

496/8=62

Hope this helps!

Answer Link

Otras preguntas

Explain why a roller coaster’s second hill cannot be taller than the first hill.
Solve the following systems of equations: 4x+5y=-4 4x+3y=12 X=? Y=?
If my final exam is worth 7% if my grade and I have an 89 in the class how much will that effect my grade, If I get an 80 on the final?
Please please help me out
Given eight different sizes hats and three people, in how many ways can the three people be given a hat
Many ionic and covalent compounds dissolve well in water. This is because (2 points) the temperature of liquid water is high enough to allow anything to mix wel
Mrs. Rodriguez has a blueprint of her new house. The actual living room has a width of 20 feet and a length of 24 feet. If the scale used to make the blueprint
Voy a la República Dominicana para visitar a mis _________ (relatives) .
How do I describe the shape of a histogram?​
wskaż trzy zasady moralne składające się na model etyki condrawoskiej