In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Rob is balancing his checkbook. his beginning checking account balance was $1. he deposited a check for $77 from his part-time job and $37 in cash that he recei
Of today's major religions, which two are monotheistic?
Explain what is so dangerous about the way an Ecstasy tablet is manufactured.
What is a value y? Y = ____
Word consciousness involves both an affective and a _____ stance toward words. words. A. poetic B. cognitive C. controlled D. discerning
To create a panoramic photograph, you need to overlap multiple photographs. True False
Which species has the smaller bond angle, h3o+ or h2o?
Please help me thank you very much.
PLZ HELP MATH QUESTION 4. Graph the function show all work f(x) = 3/2 x - 4
identify the polynomial written in asceding order. 3x3 - 5x2 + 4x - 7 -5x2 + 4x + 3x3 - 7 -7 + 4x - 5x2 + 3x3 4x + 3x3 - 7 - 5x2