Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Alicia is a resident of the maldives, a chain of low-lying islands in the indian ocean. she is planning to buy a car. her friend jerome has advised her to buy a
How long is a presidential term in mexico?
I hate this part I need help for 4 and 5 is it a b c or d
(4508-540):x=16 как сделать
Explain the importance of managing work life balance?
Which river did farmers living in the west use to transport their goods to new orleans?
example of foreshadowing or flashback
Which fallacy occurs when irrelevant evidence is used to support an argument
Your parents have a realized income of $1,046.78/every 2 weeks. How much should the monthly housing expense budget be to stay within acceptable limits?
Write 0.23 as a percent