What is the preferred approach to risk mitigation?

-Tolerate
-Transfer
-Terminate
-Treat

Respuesta :

oeerivona oeerivona
  • 08-01-2021

Answer:

The correct option is;

Terminate

Explanation:

Termination of the risk is equivalent to elimination of the risk by avoiding the activity that brings about the risk or by using a different process that does not include the risk observed in the previous process option

When the reward far outweigh the risk, it may be decided to terminate or eliminate the risk and miss the reward and also terminate the likelihood of the losses to be incurred.

Answer Link

Otras preguntas

17+(-4)-4/5j-2/5j+6​
PLEASE HELP ASAP! What is the area of the trapezoid?
liquids are fluids but gases are not true or false​
help pppppppppllllllllllllllllsssssssssss
Indira Gandhi became India’s first female prime minister because
Which could be used to monitor the rate of photosynthesis A. Oxygen production B. Water production C. Hydrogen production D. Carbon dioxide production
The official head of the senate is the ___ A) president of the United States B)Vice President C) president pro tempore D) majority leader E) chief whip
Consider three resistors with unequal resistances connected in series to a battery. Which of the following statements are true? The voltage across each of the
Need help on 5-12! Its geometry.
What were the similarities between the Native American and the White US settlers in the gold rush?