32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the
same work by 16 workers working 8 hours per day?

Respuesta :

mhanifa
mhanifa mhanifa
  • 03-09-2021

Answer:

  • 45 days

Step-by-step explanation:

Total man hours:

  • 32*30*6 = 5760

Required days:

  • 5760/(16*8) = 45
Answer Link

Otras preguntas

Besides giving young men a job, what was one of the primary purposes of the Civilian Conservation Corps? A. to limit population growth B. to help young coupl
If f(x)=x^3+3x+5 what is f(a+h)
What is the volume of this oblique cone? 432π cm³ ​ 324π ​ cm³ ​ 288π ​ cm³ ​ 144π ​ cm³
Why does biodiversity matter?
Find the slope of the line that passes through each pair of points 7,3 5,1
How does WTO assist global trade?
Which descriptions are matched with the appropriate amendment from the bill of rights
What is the dimensional analysis conversion of 27.8 liters to cm3?
thinking about and listing ones options in the process of dicision making include all of the following EXCEPT
Which side is the longest ? The shortest?